Norman Water Treatment Plant
October 7, 2022 Melanie ChaneyOVERVIEW
- Owner // City of Norman, Oklahoma
- EOR // Frankfurt-Short-Bruza
- General Contractor // BRB Contractors
- Average Drive Torque // 5,500 ft-lb
- Test Load // 30kips
PROJECT DESCRIPTION
The growing pains of most cities are felt first in the utility sector and Norman Oklahoma was not exempt. The expansion of the water treatment plant had a few obstacles to overcome the greatest of which was how to excavate 15′ below grade without undermining existing equipment and structures.
SOIL DESCRIPTION
SOLUTION
As excavation progressed, helical tieback anchors were used to stabilize the Sheet-pile wall shoring surface. The helical tieback anchors were installed through an opening cut in the sheet piling and the sheet piling was then secured with a short steel I-beam whaler. The helical tiebacks were installed quickly and immediately ready to load resulting in rapid project completion.
Per the EOR design the Piles were installed at the required angle. The design required that 33% of the Piles be proof loaded to the Ultimate Design Capacity before being locked off at the working load. Each helical tieback anchor was driven to a pre-determined installation torque. The sketch (to the right) shows the excavation and the proper angle specified to install the helical anchors.
Once the helical anchors were installed a steel I-beam whaler was attached and proof loading was preformed to confirm capacity.